Suing Contractors for Delays 

Suing a Contractor for Construction Delays in Colorado

Key Takeaway: When a Colorado construction project experiences significant delays, the parties’ rights often depend on the construction contract, the reason for the delay, the project schedule, and whether required notices were timely provided. Before terminating a contractor or asserting substantial delay damages, homeowners and project owners should document the delay, review the contract carefully, and determine whether the contractor has a contractual right to additional time.

Construction delays are a frequent source of disputes on residential and commercial projects in Colorado. A project may fall behind because of poor scheduling, inadequate staffing, subcontractor problems, design changes, permitting issues, material shortages, weather, defective work that must be corrected, or circumstances outside either party’s control.

The cause of the delay matters. So does the contract.

A contractor may be responsible for some delays while being entitled to additional time or compensation for others. Determining which party bears responsibility can become one of the central issues in a construction dispute.

1. Excusable, Non-Excusable, and Compensable Construction Delays

Construction contracts commonly distinguish among different types of project delays.

Non-Excusable Delays

A non-excusable delay generally involves a delay for which the contractor is responsible.

Examples may include:

  • Inadequate staffing
  • Poor scheduling or project management
  • Failure to coordinate subcontractors
  • Improper sequencing of trades
  • Failure to timely order materials when the delay was reasonably avoidable
  • Abandoning the project for extended periods
  • Time spent correcting defective work for which the contractor is responsible

Depending on the contract and circumstances, a contractor responsible for a non-excusable delay may be denied additional time and may be responsible for actual or liquidated damages caused by the delay.

Excusable, Non-Compensable Delays

Some delays arise from circumstances beyond the reasonable control of either party.

Depending on the contract, examples may include unusually severe weather, certain labor disruptions, governmental actions, fires, natural disasters, or other force-majeure events.

These delays may entitle the contractor to additional time without necessarily entitling either party to monetary damages.

Whether a particular event qualifies as an excusable delay depends heavily on the language of the construction contract.

Compensable Delays

A contractor may also encounter delays caused by the owner, developer, architect, or others for whom the owner is responsible.

Examples may include:

  • Failure to provide timely site access
  • Delayed design decisions
  • Late approvals
  • Owner-directed changes
  • Incomplete plans or specifications
  • Interference with the contractor’s work

Depending on the contract, these delays may entitle the contractor to additional time and compensation for increased project costs.

2. Review the Contract’s Completion Date and Delay Provisions

The construction contract is usually the starting point for evaluating a delay claim.

Important provisions may address:

  • Commencement dates
  • Substantial-completion dates
  • Final-completion dates
  • Project milestones
  • Schedule updates
  • Extensions of time
  • Weather delays
  • Force majeure
  • Owner-caused delays
  • Change orders
  • Written notice requirements
  • Liquidated damages
  • No-damages-for-delay provisions
  • Suspension and termination rights

Does the Contract Say “Time Is of the Essence”?

A contract may expressly state that time is of the essence, making timely performance an important contractual obligation.

But the absence of those exact words does not necessarily mean that a contractor can take as long as it wants to complete the project.

A specified completion date may still be enforceable depending on the language of the agreement and the circumstances surrounding the project. And where the agreement does not establish a definite time for performance, Colorado law may require performance within a reasonable time.

For this reason, delay disputes should not be evaluated solely by looking for the phrase “time is of the essence.”

Pay Attention to Written Notice Requirements

Many construction contracts require a party seeking additional time or delay damages to provide written notice within a particular period after the delaying event occurs.

AIA, ConsensusDocs, and custom construction agreements may contain detailed procedures governing when and how a delay claim must be submitted.

Failure to comply with contractual notice requirements can significantly affect a party’s ability to recover delay damages or obtain an extension of time.

3. No-Damages-for-Delay and Liquidated-Damages Clauses

Two contract provisions can have a major effect on construction-delay disputes.

No-Damages-for-Delay Clauses

A no-damages-for-delay clause generally limits a contractor’s remedy for delay to additional time rather than monetary compensation.

Colorado courts generally recognize these clauses on private projects. However, whether a particular provision applies depends on its wording and the circumstances. Colorado also recognizes exceptions, including situations involving active interference with the contractor’s performance.

Public construction projects are treated differently.

Under C.R.S. § 24-91-103.5, a provision in a Colorado public works contract that attempts to waive a contractor’s right to recover costs, damages, or an equitable adjustment for delays caused in whole or in part by acts or omissions within the contracting public entity’s control is void and unenforceable.

Liquidated Damages for Late Completion

Some construction contracts specify a fixed amount of damages for each day the project remains incomplete beyond the contractual deadline.

For example, the contract might provide for $250 or $500 per day in liquidated damages.

Under Colorado law, a liquidated-damages provision is generally enforceable when:

  • The parties intended to establish liquidated damages rather than a penalty;
  • The agreed amount was a reasonable estimate of the anticipated damages when the contract was made; and
  • The actual damages that might result from a breach were difficult to determine when the parties entered the contract.

A liquidated-damages provision that operates simply as a punishment may be unenforceable as a penalty.

An owner’s own contribution to the project delay may also affect the owner’s ability to recover liquidated damages.

4. Give Required Notice Before Terminating a Contractor for Delay

Terminating a contractor in the middle of construction can create significant legal and practical consequences.

Before terminating, the owner should review the contract carefully to determine whether it requires:

  • Written notice of default
  • A notice to cure
  • A particular cure period
  • Notice to the architect or other project representative
  • An opportunity for the contractor to provide additional labor or resources
  • Certification by an architect or other third party
  • Notice to the contractor’s surety

Many construction contracts require the owner to give the contractor a specific opportunity to cure a failure to diligently prosecute the work before termination.

If the owner terminates without complying with the contractual procedure, the contractor may argue that the owner—not the contractor—committed the material breach.

That can turn what appeared to be a strong delay claim into a wrongful-termination dispute.

What If the Delay Is Connected to Defective Work?

A delayed project may also involve defective construction.

If a homeowner intends to pursue a construction-defect claim against a construction professional, Colorado’s Construction Defect Action Reform Act may require compliance with the statutory Notice of Claim process before filing suit.

CDARA and contractual termination requirements are separate issues, so compliance with one should not be assumed to satisfy the other.

5. What Damages Can Be Recovered for Construction Delays?

Recoverable damages depend on the contract, the cause of the delay, foreseeability, proof of causation, and any contractual limitations on damages.

Depending on the circumstances, delay damages may include:

  • Additional rental or temporary housing costs
  • Additional financing or interest expenses
  • Increased construction costs
  • Extended general conditions
  • Additional project-management expenses
  • Increased labor or equipment costs
  • Loss-of-use damages
  • Liquidated damages established by contract

Commercial construction claims may also involve extended overhead, lost productivity, acceleration costs, and other schedule-related damages.

However, construction contracts frequently contain waivers of consequential damages, no-damages-for-delay provisions, limitations of liability, and strict notice requirements that may substantially affect what can be recovered.

6. Can Delay-Related Costs Be Included in a Mechanic’s Lien?

Not every type of delay damage belongs in a Colorado mechanic’s lien.

Colorado mechanic’s liens generally secure qualifying amounts attributable to labor, services, materials, equipment, and other value furnished to improve the property. Purely consequential damages—such as lost profits arising from a delay—should not automatically be treated as lienable merely because they arise from a construction dispute.

The analysis can become more complicated when a delay causes the contractor actually to incur additional labor, material, equipment, or other project costs.

Because including amounts that are not properly lienable can create substantial risk, contractors and subcontractors should carefully distinguish between amounts attributable to work actually furnished to the project and separate breach-of-contract or consequential delay damages.

C.R.S. § 38-22-128 also provides significant consequences when a claimant knowingly records a lien for an amount greater than is due without a reasonable possibility that the claimed amount is owed.

What Should You Do If Your Construction Project Is Months Behind Schedule?

A serious construction delay should be addressed before the relationship between the owner and contractor completely deteriorates.

Start by gathering the contract, project schedule, change orders, payment records, emails, text messages, photographs, daily reports, and communications explaining why work has stopped or fallen behind.

The next step is to determine:

  • What completion date the contractor actually promised;
  • What events caused the delay;
  • Whether the contractor is entitled to additional time;
  • Whether required delay notices were provided;
  • Whether the contract allows recovery of damages;
  • Whether a notice to cure is required; and
  • Whether termination is legally and strategically appropriate.

Sweeney Construction Law represents homeowners, contractors, developers, and other project participants in construction-delay and contract disputes throughout Colorado.